Stafford County Board of Supervisors has been working very hard to keep the public informed about the Kraken Loop. Visit the portal Stafford County Created for videos of meetings and the most recent updates.
To date, Stafford has
- heard citizen concerns about the Kraken
- passed a resolution titled A RESOLUTION TO OPPOSE ALIGNMENTS OF THE PROPOSED NORTH ANNA-KRAKEN LOOP ELECTRIC TRANSMISSION PROJECT THAT WOULD NEGATIVELY IMPACT STAFFORD COUNTY AND REQUEST ADDITIONAL ENGAGEMENT FROM DOMINION ENERGY
- created a web portal to communicate what's happening with the public
- written a letter to the SCC
- written a letter to Dominion, requesting their attendance at a Jan 2026 public meeting in the county (Dominion is not participating)
- scheduled a listening meeting for Thursday, January 29, 2026, at 6:30 p.m. at Brooke Point High School, located at 1700 Courthouse Rd, Stafford, VA 22554
- hired an attorney to represent the county's interests
What is Dominion required to provide to Stafford County?
E. Every electric utility that is responsible for the construction, operation, and maintenance of electric transmission lines of 150 kilovolts or more shall furnish reasonable information requested by the local planning commission having authority to prepare a comprehensive plan within the utility's certificated service area relative to any electric transmission line of 150 kilovolts or more that may affect the locality's comprehensive plan. If the locality seeks to include the designation of corridors or routes for electric transmission lines of 150 kilovolts or more in its comprehensive plan, the local planning commission shall give the electric utility a reasonable opportunity for consultation about such corridors or routes. The electric utility shall notify the chief administrative officer of every locality in which the electric utility plans to undertake construction of any electric transmission line of 150 kilovolts or more, prior to the filing of any application for approval of such construction with the State Corporation Commission, of its intention to file any such application and shall give the locality a reasonable opportunity for consultation about such line. ( https://law.lis.virginia.gov/vacode/title15.2/chapter22/section15.2-2202/ )
Dominion is required by law to consult with our board of supervisors and planning commission. Write to your board of supervisors rep to find out if Dominion has done this.